Cement plant control and energy monitoring
Plant control moved from Siemens WinCC to GE iFIX at Nagarjuna Cements, and an energy monitoring system on 43 power meters at Vishnu Cements.
- Cement
- Migration
- Energy
Control of a 20-hour batch process in an R&D furnace for DRDO's Research Centre Imarat, built by Therelek Systems.
Research Centre Imarat, DRDO's missile systems laboratory in Hyderabad, ordered a furnace from Therelek Systems for an R&D application. The furnace runs a 20-hour batch process with vacuum pumps and reactive gases, so its control had to sequence the process exactly and shut it down safely.
A GE VersaMax PLC with about 300 I/O sequences the vacuum pumps, the flow of reactive gases and the safety shutdown, and GE iFIX gives the operators the process, alarms and batch reports. Our team wrote the complete ladder logic, configured the SCADA and commissioned the system at RCI.
The PLC runs the vacuum pumps, admits the reactive gases in order and holds each step of the 20-hour batch, with interlocks and a safety shutdown if conditions leave their limits.
GE iFIX shows the furnace and its auxiliaries, raises alarms and produces the batch reports.
We supplied the GE VersaMax PLC, about 300 I/O, and the iFIX SCADA, wrote the complete ladder logic, configured the SCADA and commissioned the system at RCI.
Photographs from this project are being added.
PLC panels, marshalling and SCADA workstations built to our drawings, wired, tested and documented before dispatch.
Remote data acquisition, energy monitoring, batch control, tank farm inventory and furnace automation for chemicals, cement, sugar, rice and rubber plants.
Plant control moved from Siemens WinCC to GE iFIX at Nagarjuna Cements, and an energy monitoring system on 43 power meters at Vishnu Cements.
Measurement and control across the process industries.
Tell us what you are planning, even if the details are still rough. We reply with a technical approach and an offer.